Enhancing on site safety: Electrical Upgrades at Portsmouth Guildhall

Written by Dave Houghton | 21-Oct-2025 14:39:29

Assessing the Need for Electrical Upgrades at Portsmouth Guildhall

Portsmouth Guildhall, a landmark at the heart of the city, faced significant challenges related to its aging electrical infrastructure. The need for an upgrade was underscored by outdated systems that no longer complied with modern safety standards.

The presence of asbestos-containing risers added a layer of complexity, necessitating expert intervention to ensure the safety of both staff and visitors. This project was not just a routine upgrade; it was a vital step in preserving the integrity and functionality of a historic venue while aligning it with contemporary safety requirements.

The Guildhall's management recognised the urgency of the situation and sought specialised expertise to address these challenges. The goal was to overhaul the existing electrical setup comprehensively.

This included installing new electrical risers and distribution boards to enhance efficiency and safety. The project was designed to be executed without interrupting the daily activities at the Guildhall, which demanded meticulous planning and execution.

Overcoming Challenges with Innovative Solutions

One of the most daunting challenges faced during the project was the need to perform core drilling from the basement to the third floor while the Guildhall remained operational. This required innovative solutions to minimise disruption.

The project team devised a strategy to perform these tasks during off-peak hours, ensuring that the work did not interfere with ongoing events and activities. Additionally, utilising an existing lift shaft for new bus bar risers helped streamline the installation process, minimising the need for invasive structural changes.

The team also had to contend with inherited test sheets from previous contractors, which revealed compliance issues that needed immediate resolution. This necessitated quick adjustments, including rewiring and circuit alterations, to meet current standards.

Through close collaboration with the client, the team successfully addressed these issues, ensuring that the Guildhall's electrical systems were not only upgraded but also fully compliant with modern safety regulations.

Implementing Safety Measures Amidst Operational Activities

Safety was a paramount concern throughout the project, particularly given the ongoing operations at Portsmouth Guildhall. The project team took extensive measures to ensure that all safety protocols were strictly adhered to.

This involved maintaining the functionality of the fire alarm system during core drilling and other potentially disruptive activities. By scheduling work during less busy times and keeping all stakeholders informed about the project timeline and potential impacts, the team was able to maintain a safe environment for everyone involved.

Moreover, new fire-rated doors were installed as part of the upgrade, providing an additional layer of safety. These measures were not just about compliance; they were about ensuring that the Guildhall remained a safe space for its staff and visitors, reinforcing confidence in the venue's ability to host events without compromising on safety.

Effective Fatigue Management for Enhanced Performance

Managing fatigue among the project team was another critical aspect of ensuring the project's success. The demanding nature of the work, combined with the need to transition between day and night shifts, posed a significant risk of fatigue-related incidents.

To mitigate this, the team implemented a robust fatigue management system, utilising two separate teams to handle different shifts. This approach allowed for adequate rest periods and minimised the risk of fatigue impacting performance.

Handovers between the day and night teams were carefully managed to ensure continuity and maintain the momentum of the project. A risk reporting system was also established, allowing team members to flag any issues related to fatigue, ensuring that no one was assigned to demanding tasks without being fully rested and alert.

This focus on well-being was crucial in maintaining high levels of performance and safety throughout the project.

Collaborative Efforts to Ensure Compliance and System Integrity

Collaboration was at the heart of the project's success. The team worked closely with Portsmouth Guildhall's management to ensure that all aspects of the upgrade were aligned with compliance requirements and the venue's operational needs.

This collaborative approach extended to addressing unforeseen challenges, such as inherited compliance issues from previous contractors. By working together, the team and the client were able to navigate these complexities effectively, ensuring that the final outcome met all necessary standards.

The integration of new sub-mains from the main switchboard to the new risers was a critical component of the upgrade, enhancing the system's overall integrity. The team also successfully transferred existing circuits to new distribution boards, removing outdated components and ensuring a seamless transition to the new system.

Through meticulous planning and execution, the project not only met but exceeded the initial scope, resulting in a safer and more efficient electrical infrastructure for the Guildhall.

Reflections and Learnings from the Project's Success

The successful completion of the electrical upgrade at Portsmouth Guildhall provided valuable insights and learnings for future projects. The team's ability to manage complex challenges while ensuring safety and compliance was a testament to their expertise and dedication.

The project underscored the importance of thorough planning, effective communication, and adaptive problem-solving in delivering successful outcomes.

Feedback from the site highlighted the team's professionalism and ability to handle the various complexities associated with the project. Despite the increase in the final cost due to unforeseen issues, the Guildhall's management expressed satisfaction with the enhanced safety and functionality of the upgraded systems.

This project not only achieved its immediate objectives but also set a benchmark for future renovations, demonstrating the value of investing in comprehensive, safety-focused upgrades.